WORK SCHEDULE

There is no night work scheduled for Rt. 9 the week beginning 9-7-08.
Beginning on Monday - Daytime - 9-8-08 thru Friday 9-12-08 work will begin on Underground Traffic Conduit between Reservoir Rd. and High St.
Note: The Raised structures on Route 9 are in the final stages of being completed. This work has to be done before the final layer of bituminous asphalt is completed.
Finish Paving (the final layer) of Route 9 will begin on Sunday Night 9-14-08.
Aggregate Industries appreciates your patience during the construction work being done on Route 9 in Brookline, Ma.
Limit of work is on Route 9 in the Town of Brookline, Ma from the Newton Town Line to High St.

 

More scheduling information >>

PLEASE SUBMIT YOUR COMMENTS AND FEEDBACK >>

Learn about work zone safety
Aggregate Industries

Welcome to PaveRt9.com — a public service site providing construction project information to the commuting public.

The project in Brookline begins at the Newton-Brookline Town Line at station 0+00 Brookline, then continues along Route 9 (Boylston Street) easterly in the town of Brookline to the end of project at station 145+00 at the end of State Highway Layout before the intersection of High Street and Washington Street bear Brookline Village.

The scope of work involved on the Route 9 project requires the use of heavy construction machinery, including trucks, milling machines, pavers and other types of heavy equipment. Click here for more information about our methods and about any noise generated.

PaveRt9 is brought to you by Aggregate Industries. We are committed to safety, it is our number one priority.

Please remember: Safety is a two way street. We are counting on the commuting public to help us attain our goal of ZERO ACCIDENTS.